Please note that the timing of the project tasks may change due to the progress of the project.
Project Tasks
Due Date
Remarks
Project Team Convened
06/04/2010
Completed
Advisory Board Members Invitation
11/04/2010
Completed
Advisory Board Members Convened
24/04/2010
Completed
Site Orientations for Advisory Board As Needed
24/04/2010
Completed
Advisory Board answers the Research Questions
27/06/2010
Completed
Project Staff produce the "Short List" for Survey Questions
02/07/2010
Completed
Sent out Survey Form to Advisory Board Members
25/07/2010
Completed
Advisory Board Submit Survey Form
02/08/2010
Completed
First Draft of Report
19/08/2010

Final Draft of Report Endorse by Advisory Board
23/08/2010

Report in Layout and Design
27/08/2010

Advance Copy to Advisory Board in PDF Format
30/08/2010

Report Ready for Release
31/08/2010